Hybrid Annuity Model (HAM) Funding Explained
Under the Hybrid Annuity Model (HAM) for infrastructure projects, what percentage of the project cost is funded by the government during construction?
Explanation in English
Correct Answer Explanation
The Hybrid Annuity Model (HAM) is a public-private partnership (PPP) model for infrastructure development. Under this model, the government commits to funding 40% of the total project cost during the construction phase. This amount is disbursed in milestone-linked installments, reducing the financial burden on the private developer.
Incorrect Options Analysis
- 100%: This represents a fully government-funded project, typically under an Engineering, Procurement, and Construction (EPC) model, not HAM.
- 60%: This is the portion of the project cost that the private developer is responsible for financing through a mix of debt and equity.
- 25%: This percentage is not a standard figure for the government's contribution under the HAM framework.
हाइब्रिड एन्युटी मॉडल (HAM) फंडिंग प्रश्नोत्तरी
बुनियादी ढांचा परियोजनाओं के लिए हाइब्रिड एन्युटी मॉडल (HAM) के तहत, निर्माण के दौरान परियोजना लागत का कितना प्रतिशत सरकार द्वारा वित्त पोषित किया जाता है?
Explanation in Hindi
सही उत्तर की व्याख्या
हाइब्रिड एन्युटी मॉडल (HAM) बुनियादी ढांचे के विकास के लिए एक सार्वजनिक-निजी भागीदारी (PPP) मॉडल है। इस मॉडल के तहत, सरकार निर्माण चरण के दौरान कुल परियोजना लागत का 40% वित्त पोषण करने के लिए प्रतिबद्ध है। यह राशि मील के पत्थर से जुड़ी किस्तों में वितरित की जाती है, जिससे निजी डेवलपर पर वित्तीय बोझ कम होता है।
गलत विकल्पों का विश्लेषण
- 100%: यह पूरी तरह से सरकार द्वारा वित्त पोषित परियोजना का प्रतिनिधित्व करता है, जो आमतौर पर इंजीनियरिंग, प्रोक्योरमेंट और कंस्ट्रक्शन (EPC) मॉडल के तहत होता है, न कि HAM के तहत।
- 60%: यह परियोजना लागत का वह हिस्सा है जिसे निजी डेवलपर ऋण और इक्विटी के मिश्रण के माध्यम से वित्तपोषित करने के लिए जिम्मेदार है।
- 25%: यह प्रतिशत HAM ढांचे के तहत सरकार के योगदान के लिए एक मानक आंकड़ा नहीं है।